The following is the breakdown of plants that will be closed or placed on standby.
Plant / Status / Timing
Assembly
Orion, Mich. - Standby Capacity - September 2009
Pontiac, Mich. - Close - October 2009
Spring Hill, Tenn. - Standby Capacity - November 2009
Wilmington, Del. - Close - July 2009
Stamping
Grand Rapids, Mich. - Close - June 2009 (previously announced)
Indianapolis, Ind. - Close - December 2011
Mansfield, Ohio - Close - June 2010
Pontiac, Mich. - Standby Capacity - December 2010
Powertrain
Livonia Engine, Mich. - Close - June 2010
Flint North Components, Mich. - Close - December 2010
Willow Run Site, Mich. - Close - December 2010
Parma Components, Ohio - Close - December 2010
Fredericksburg Components, Virg. - Close - December 2010
Massena Castings, N.Y. - Closed - May 1, 2009 (previously announced)